DU-Fisher Early Learning Center-Condenser Replacement

Working closely with DU on the Fisher Early Learning Center, one of several projects we completed was replacing their outdoor condenser unit. This project involved several tasks: first, the removal of the existing condensing unit, followed by the capture and disposal of the existing refrigerant and other fluids. Next, a new 40-ton condensing unit with digital scroll capacity control and hail guards was installed, along with new R-410A refrigerant. Modifications to the existing electrical system were made as needed to accommodate the new installation, and adjustments were also made to the exposed refrigerant lines to connect to the new unit. This work was specifically planned and timed during a short outage window to ensure the operations of the facility were not impacted.